 Progres Normalisasi Saluran Jl Musik Raya Capai 45 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Channel Normalization at Jalan Musik Raya Reaches 45 Percent

A water channel, which is still being normalized on Jalan Musik Raya, RW 07, Pegangsaan Dua Urban Village, Kelapa Gading, North Jakarta has reached 45 percent. It is targeted to be completed in three weeks ahead.

Prior to repair, it was full of mud and unoptimal. I saw its sheetpiles also broken

Normalization is conducted up to 158 meters length. It includes repairing and widening of channel from 60 centimeters into 1 meter. 

Normalization Conducted on Jalan Danau Buyan Kecil's Channel

"Prior to repair, it was full of mud and unoptimal. I saw its sheetpiles also broken," he expressed, Monday (2/18).

It is also downstream of the micro channel in the residential area, RW 05. As a result, because of unoptimal channel, it triggers a puddle.

Despite the work is unfinished, water from the channel can already flow smoothly towards the Accordion connecting channel.

"After this work, hopefully it can overcome puddle in RW 05, Pegangsaan Dua," he hoped.

Linked News
Popular News indeks
  1. Jakarta-France Strengthen Cooperation in Various Sectors

    access_time11-04-2025 remove_red_eye522 personDessy Suciati
  2. Three South Jakarta Parks Set for Revitalization and 24-Hour Operation

    access_time12-04-2025 remove_red_eye453 personDessy Suciati
  3. 60 Joint Personnel Conduct Community Work in Karet Tengsin

    access_time13-04-2025 remove_red_eye395 personBudhi Firmansyah Surapati
  4. Free Transportation Services to Facilitate Residents' Mobility

    access_time17-04-2025 remove_red_eye275 personDessy Suciati
  5. Jakarta to be Designed as a Film City

    access_time13-04-2025 remove_red_eye273 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik